How Much Gravel Under a Concrete Slab? (Depth, Yards & Tons)
The gravel base is the cheapest insurance in a concrete project. Depth by slab use, yards-and-tons tables for standard footprints, a worked example, and which stone to order.
By the Cubic Yard Calculator team · Last updated October 2026
The short answer
Put 4 inches of compacted gravel under patios, walkways, and shed pads, and 6 inches under driveways, parking pads, and garages that carry vehicles. The math is one formula: length × width × depth (in feet) ÷ 27 = cubic yards, then multiply yards by 1.4 for tons. A 20×20 slab at 4 inches needs about 5 yards (7 tons); at 6 inches it needs about 7.5 yards (10.5 tons). Order #57 stone or crusher run — never pea gravel — and compact it in lifts.
Depth by slab use
Depth is decided by load, not by preference. The gravel sits under the concrete — the slab itself (typically 4 inches for residential work) pours on top of the finished base:
| Slab use | Gravel depth | Why |
|---|---|---|
| Patio, walkway | 4″ | Foot traffic only; drainage and frost protection are the jobs |
| Shed pad, small outbuilding | 4″–6″ | 4″ for light sheds; 6″ for heavy equipment or riding mowers stored inside |
| Driveway / parking pad | 6″ | Vehicle loads; resists rutting and pumping under tires |
| Garage floor | 6″ + engineered note | Vehicles plus walls bearing on the edge — confirm with local code; many jurisdictions want 6″ minimum |
| Structural / commercial | Per plans | Engineer specifies depth, stone type, and compaction testing — do not DIY the spec |
Clay soil pushes everything one step deeper in practice: if your subgrade is clay, use the 6-inch column even for a shed pad, and lay woven geotextile fabric between the soil and the stone so the gravel does not sink into the mud over the seasons.
The math: one worked example
Convert depth to feet first — 4 inches = ⅓ foot, 6 inches = ½ foot — then it is a single multiplication:
20 × 20 slab at 4 inches: 20 × 20 × (1/3) ÷ 27 = 4.94 cubic yards, so order 5 yards (about 7 tons at 1.4 tons per yard). Add 10% overage for compaction and spillage and the practical order is 5.5 yards.
Same slab at 6 inches: 20 × 20 × 0.5 ÷ 27 = 7.41 cubic yards, so order 7.5 yards (about 10.5 tons); with overage, 8.25 yards.
Every entry in the tables below is built from that same formula. For an odd footprint, our gravel calculator runs it in one pass — and when you are ready to size the concrete itself, the concrete calculator handles the pour.
Yards and tons by footprint: 4-inch base
Tons use gravel's 2,800 lbs/yd³ (×1.4). The “order” column adds 10% overage, rounded to what suppliers sell:
| Footprint (ft) | Sq ft | Yards | Tons | Order |
|---|---|---|---|---|
| 10 × 10 | 100 | 1.23 | 1.7 | 1.5 yd |
| 12 × 16 | 192 | 2.37 | 3.3 | 2.75 yd |
| 16 × 20 | 320 | 3.95 | 5.5 | 4.5 yd |
| 20 × 20 | 400 | 4.94 | 6.9 | 5.5 yd |
| 24 × 24 | 576 | 7.11 | 10.0 | 8 yd |
| 24 × 30 | 720 | 8.89 | 12.4 | 10 yd |
Yards and tons by footprint: 6-inch base
| Footprint (ft) | Sq ft | Yards | Tons | Order |
|---|---|---|---|---|
| 10 × 10 | 100 | 1.85 | 2.6 | 2 yd |
| 12 × 16 | 192 | 3.56 | 5.0 | 4 yd |
| 16 × 20 | 320 | 5.93 | 8.3 | 6.5 yd |
| 20 × 20 | 400 | 7.41 | 10.4 | 8.25 yd |
| 24 × 24 | 576 | 10.67 | 14.9 | 12 yd |
| 24 × 30 | 720 | 13.33 | 18.7 | 15 yd |
Priced per ton at the quarry? Our gravel-to-tons calculator converts either direction so you can compare a per-yard quote against a per-ton one.
Which gravel to order — and which to refuse
Two products are correct for a slab sub-base. #57 stone — clean, angular crushed rock about ½ to 1 inch — drains freely and locks together under compaction; it is the default under most residential slabs. Crusher run (also sold as road base or dense-grade aggregate) is the same angular stone plus crusher dust, which packs into an even harder, tighter layer; choose it where the subgrade is soft or the slab carries vehicles. The product to refuse is pea gravel: its rounded stones shift under load and never interlock, so the base migrates and the slab settles unevenly. Sand alone is wrong for the same reason — it pumps and washes out from under the slab edge.
Building the shed first and the slab later? Our shed-base gravel guide covers the pad-only version of this job, where the gravel is the finished surface rather than a sub-base.
Vapor and moisture barrier note
For any interior slab — garage, basement, workshop — lay 10-mil polyethylene sheeting over the compacted gravel before the pour, with seams lapped 6 inches and taped. Ground moisture wicks up through concrete by capillary action, and the poly breaks that path; skip it and you get damp floors, musty smells, and flooring that fails to bond. For exterior slabs like patios and walkways, do the opposite: no vapor barrier. Outdoors it traps water under the slab instead of excluding it — drainage through the gravel base is the moisture strategy there.
Compaction in lifts — the step that decides everything
Gravel only becomes a base once it is compacted, and compaction only reaches a few inches deep per pass. Place the stone in 3–4 inch lifts: spread a lift, run a plate compactor over it until it stops leaving marks, then spread the next. Dumping the full 6 inches at once and rolling the top compacts nothing below the surface — the bottom stays loose, settles over the first wet season, and the slab above cracks along the settlement line. Rent the plate compactor for the day; it is the cheapest tool on the job and the one most skipped. Water each lift lightly before compacting — damp stone packs tighter than dry.
What the gravel base costs
Typical U.S. ranges for the stone itself, before the concrete:
| Cost line | #57 stone / crusher run |
|---|---|
| Per cubic yard (quarry gate) | $35–$65 |
| Delivery, single load within ~20 mi | $75–$150 |
| 20 × 20 slab, 4″ base (~5.5 yd delivered) | $270–$510 |
| 24 × 30 slab, 6″ base (~15 yd delivered) | $600–$1,125 |
That is usually under 10% of the total slab project — concrete, forming, and labor dominate. It is also the part of the job you cannot redo after the pour, which is exactly why skimping it is the most expensive saving in concrete work. Wondering what a cubic yard of anything actually weighs? Our cubic-yard weight guide covers every common material on one chart.
Common mistakes
Pea gravel as sub-base. Rounded stone migrates — angular #57 or crusher run only. One deep lift. Compact in 3–4 inch passes or the bottom never densifies. Skipping fabric on clay. The stone sinks into the mud and the “base” becomes a rumor. Vapor barrier outdoors. It traps water under exterior slabs; drainage is the strategy there. Exact-yard ordering. Compaction eats 10–15% of loose volume; the second delivery fee always exceeds the extra half yard. Gravel but no drainage plan. The base moves water down and out — make sure “out” exists by grading soil away from the slab edge.
Gravel Under a Concrete Slab FAQ
Straight answers, no fluff. Then run your own numbers above.
How thick should gravel be under a concrete slab?
4 inches for patios, walkways, and shed pads; 6 inches for driveways, parking pads, and garages that carry vehicles. The gravel goes under the concrete, not in it — the slab thickness itself (usually 4 inches for residential) sits on top of the compacted base. Anything structural or commercial follows engineered plans.
How much gravel do I need for a 20x20 concrete slab?
At 4 inches deep: 20 × 20 × (1/3) ÷ 27 = 4.94 cubic yards, so order 5.5 yards (about 7.7 tons with 10% overage). At 6 inches deep: 7.41 yards, so order about 8.25 yards (~11.5 tons). See the footprint tables below for other sizes.
What kind of gravel goes under a concrete slab?
#57 stone (clean, angular, 1/2 to 1 inch) or crusher run (angular stone with dust that packs hard). Both drain and compact well. Do not use pea gravel — its rounded shape shifts under load and never locks into a stable base, which lets the slab settle unevenly.
Do I need gravel under a concrete slab on clay soil?
Yes — especially on clay. The gravel base breaks capillary action so groundwater cannot wick up into the slab, and it gives freeze-thaw expansion somewhere harmless to go instead of heaving the concrete. On clay, use the full 6 inches, lay woven geotextile fabric between soil and stone, and make sure water drains away from the slab edge.
Can I pour concrete directly on dirt without gravel?
You can, but you inherit every problem gravel prevents: the slab wicks moisture from the soil, freeze-thaw heaves it, and soft spots in the dirt settle and crack the concrete. The gravel base is the cheapest insurance in the whole project — typically under 10% of the job cost.
Should the gravel under a slab be compacted?
Yes, in 3–4 inch lifts with a plate compactor. Dumping the full 6 inches at once and rolling only the top leaves the bottom loose, and it will settle later — taking the slab with it. Compact each lift until the compactor stops leaving marks, then add the next.
Do I need a vapor barrier over the gravel under a slab?
For any interior slab (garage, basement, workshop): yes. Lay 10-mil polyethylene sheeting over the compacted gravel before the pour, lapped and taped at seams. It stops ground moisture from migrating through the concrete into the building. For exterior slabs like patios, a vapor barrier is unnecessary and can trap water.
References
- Material densities: published bulk-material density tables cross-checked against supplier data (see /data-sources/).
- Aggregate gradations: ASTM C33 aggregate density ranges and standard stone gradations, including #57 stone.
- Pricing: published contractor cost guides and supplier listings, checked October 2026.
- All calculations use the site's published constants — see Data Sources (/data-sources/).
Run your own numbers
Reading is good. Math is better. Punch your project into the free calculator and order with confidence.