How Much Sub-Base (Crushed Stone) Do I Need?

The sub-base is the hidden layer that decides whether your driveway or patio stays flat. Depth tables, the cubic-yard formula, tons conversions by stone type, and the compaction adjustment.

By the Cubic Yard Calculator team · Last updated October 2026

The short answer

For a residential driveway, plan on 4–6 inches of compacted crushed stone; for a patio, 4 inches; for a shed base, 3–4 inches. The formula is the same as every bulk-material job: length × width × depth in feet, divided by 27 gives cubic yards, then multiply by your stone's weight — 1.4 tons per cubic yard for typical crushed stone — to get tons. A 20 × 40 ft driveway at 4 inches needs 9.88 cubic yards ≈ 13.8 tons. One catch: those are compacted depths, and you order loose material — with crusher run, add 15–20% to reach your finished depth.

What a sub-base actually does

Every paved or gravel surface that lasts is a stack of layers, and the sub-base is the load-bearing one — a bed of crushed stone laid directly on graded soil, under the surface you actually see and walk on. Its job is to spread point loads across a wider area so the soil underneath doesn't compress, rut, or pump up through the surface. Car tires, paver slabs, and shed floors all concentrate weight into small footprints; the sub-base turns those footprints into a distributed load the ground can actually carry.

Names vary and that causes real confusion. Paver installers tend to call the crushed-stone layer the “base” and the inch of sand above it the “bedding layer.” Driveway builders often say “sub-base” for the bottom stone and “base” for the middle layer in a three-layer build. A supplier may call the same material crusher run, road base, dense grade, 21A, or ABC stone. Don't get hung up on the label — ask whether the material has fines (the rock dust that lets it compact into a rigid bed). If it does, it works as a sub-base; if it's clean washed stone with no dust, it's a drainage layer, not a structural one. (In the UK this layer is called hardcore or MOT Type 1, but the math — depth × area, then convert to tons — is identical.)

The formula, then the depths

Sub-base quantity is volume math with a unit conversion at the end:

1. Measure length and width in feet. 2. Pick your compacted depth from the table below and convert inches to feet (divide by 12). 3. Multiply: length × width × depth in feet, then divide by 27 — that's cubic yards of compacted material. 4. Multiply by your stone's tons per cubic yard for the tonnage, then add the compaction adjustment (15–20% for crusher run) to get the loose quantity you actually order.

ProjectCompacted depthOrder the loose equivalentNotes
Residential driveway (cars, light trucks)4–6 in4.6–7.2 in looseGo 6 in if the soil is clay or the drive sees daily use
Heavy-vehicle pad (RV, boat, deliveries)6–8 in6.9–9.6 in looseTwo 3–4 in lifts, each compacted separately
Patio / paver base4 in~4.6 in loosePlus 1 in of bedding sand above; see our paver base guide
Shed base3–4 in3.5–4.8 in looseExtend 6–12 in beyond the shed footprint
Walkway3–4 in3.5–4.8 in loose4 in if the soil is soft or the path takes mower traffic
Gravel parking area4–6 in4.6–7.2 in looseCrown the surface ¼ in per foot for drainage

“Order the loose equivalent” assumes crusher run or road base compacted to about 17% — the midpoint of the 15–20% compaction loss these materials need (see our settlement and ordering guide for the full tables). Clean #57 stone barely compacts at all, so its loose and compacted volumes are nearly the same — but clean stone also makes a weaker sub-base, which is why crusher run is the default choice below.

Cubic yards to tons, by stone type

Suppliers usually quote sub-base by the ton and deliver by the yard, so you need both numbers. Tons per cubic yard depend on the stone — these are this site's published bulk densities, and the calculator uses the same values, so the page, the tables, and the tool can never disagree:

Stone typeLbs per cubic yardTons per cubic yardSub-base use
Crushed stone (typical)2,8001.40The default — crusher run / road base lives here
Pea gravel2,7001.35Poor sub-base: round, no interlock — skip for structure
River rock2,9001.45Same problem as pea gravel — decorative, not structural
Crushed concrete (RCA)2,9001.45Good budget sub-base where available — compacts well
Decomposed granite2,6501.325Better as a path surface than a structural sub-base

In practice: if your supplier sells “crusher run,” “dense grade,” or “road base,” use 1.4 tons per yard. Across every common crushed stone the real range is only 1.325–1.45 tons/yd³, so an estimate built on 1.4 lands within a few percent either way. Run the volume through our gravel calculator or gravel-to-tons converter and pick your stone type from the density dropdown — the weights follow automatically.

Worked examples

Driveway, 20 × 40 ft, 4 in compacted crusher run. Area: 800 sq ft. Depth: 4 ÷ 12 = ⅓ ft. Volume: 800 × ⅓ = 266.7 cu ft = 9.88 cubic yards compacted. At 1.4 tons/yd³: 9.88 × 1.4 = 13.8 tons. Add the ~17% compaction adjustment: 9.88 × 1.17 = 11.56 loose yards → order 12 yards (≈ 16.8 tons at 1.4). That's the full order — compacted depth, loose delivery, and tons in one pass.

Patio, 12 × 16 ft, 4 in compacted sub-base. 192 sq ft × ⅓ ft = 64 cu ft = 2.37 cubic yards compacted (3.3 tons at 1.4). Loose with the 15% adjustment: 2.37 × 1.15 = 2.73 → order 3 yards. Our paver base guide adds the bedding-sand inch on top of this.

Shed base, 10 × 12 ft, 4 in. 120 sq ft × ⅓ ft = 40 cu ft = 1.48 cubic yards (≈ 2.1 tons). Loose: 1.48 × 1.15 = 1.70 → order 2 yards. One delivery, one job — see our shed base guide for the full build.

Quick per-foot rule. One square foot at 4 inches deep is 0.0124 cubic yards — about 35 lb (0.017 tons) of crushed stone at 1.4 t/yd³. For a rough price check, multiply your square footage by 35 lb and by 1.4 at 6 inches instead.

Which material to actually order

The name on the ticket matters less than the particle mix. What you want is angular crushed stone with fines — stone broken by a crusher, with rock dust and chips mixed in. The dust fills the voids between the larger pieces under the plate compactor, and that's what turns loose stone into a rigid, almost pavement-like bed. Sold regionally as crusher run, ¾-inch minus, dense grade, road base, 21A, or ABC — they're the same idea in different quarries. For a side-by-side on the decorative side of the family, see our crushed stone vs pea gravel guide.

Recycled concrete aggregate (RCA) is worth asking about: it compacts well, drains acceptably, and often costs 20–40% less than virgin stone. The one caution is consistency — ask whether it's screened to a uniform size and free of rebar and trash, especially for the top inch under pavers. Decomposed granite makes a beautiful path surface but a mediocre structural sub-base; it needs about 20% extra loose to compact and still stays softer than crusher run. And skip pea gravel and river rock for structure entirely — round stones roll instead of interlocking, which is exactly what you don't want under load.

The compaction adjustment, explained

This is the step that strands DIYers a yard short. A 4-inchcompacted layer of crusher run needs roughly 4.6–4.8 inches of loose material to get there — the 15–20% the fines give up as they pack into the voids. Clean #57 stone is the opposite: it barely compacts, so loose and finished volumes are nearly equal, but you've traded away the interlock that makes a sub-base work. The rule: order loose volume, design to compacted depth, and spread the loose stone in 2 to 3-inch lifts, compacting each lift with a plate compactor (mist lightly with water between passes — damp stone compacts tighter than dry).

For driveways, see our full driveway gravel guide for the three-layer build (large base stone, #57 middle, crusher run top) with tons tables by driveway size. For ordering strategy — why the buffer beats a second delivery — our settlement guide covers the economics.

Common mistakes

Ordering compacted yards instead of loose yards. The 15–20% shortfall shows up exactly when the truck is leaving. Dumping all the stone at once and compacting the top. The bottom stays soft and settles for years — work in lifts. Using clean decorative stone as structure. Pea gravel and river rock belong on top of a path, not under a driveway. Skipping fabric on soft soil. Without a separator, the sub-base sinks into clay and you effectively lose an inch of paid-for stone. Forgetting the crown. A dead-flat driveway holds water; crown it about ¼ inch per foot from center to edge so it sheds.

Sub-Base FAQ

Straight answers, no fluff. Then run your own numbers above.

What is a sub-base, and is it different from a base layer?

The sub-base is the load-bearing layer of crushed stone laid directly on the graded soil, under the surface layer. Terminology varies by trade and region — pavers installers often call the crushed-stone layer the 'base' and the sand above it the 'bedding layer', while driveway builders say sub-base for the bottom stone and base for the middle layer. Whatever you call it, its job is the same: spread the load so the soil underneath doesn't rut.

How deep should the sub-base be for a driveway?

4 to 6 inches of compacted sub-base for a residential driveway carrying cars and light trucks; 6 to 8 inches if it takes delivery trucks, RVs, or boat trailers regularly. Patios and walkways need 4 inches compacted, shed bases 3 to 4 inches. These are compacted depths — with crusher run you order 15 to 20% more loose material to get there.

How many tons of sub-base is that per square foot?

One square foot at 4 inches deep is 0.01235 cubic yards, which at 1.4 tons per yard (typical crushed stone) weighs about 35 pounds — roughly 0.017 tons. So a 20×40 ft driveway at 4 inches needs 9.88 cubic yards, or about 13.8 tons. Multiply your area by the tons-per-yard of your stone type (1.325 to 1.45 depending on the crushed stone) to get your number.

Can I just use regular gravel instead of crusher run for a sub-base?

You can, but it performs worse. Clean gravel (no fines) doesn't compact into a rigid layer — the stones shift under load and the surface ruts. Crusher run, road base, or dense-grade aggregate include rock dust and small chips that fill the voids and lock the layer into an almost pavement-like bed under a plate compactor. Use clean gravel only for drainage layers where water needs to pass through freely.

Do I really need to compact the sub-base?

Yes — compaction is the whole point of the layer. Uncompacted stone is just expensive gravel sitting on dirt; it settles unevenly and your surface follows. Spread stone in 2 to 3-inch lifts and run a plate compactor over each one, misting lightly with water between passes. Skipping compaction is the most common reason DIY driveways and patios develop dips within two years.

Do I need landscape fabric under the sub-base?

On clay, low-lying, or soft soil, yes — lay woven geotextile fabric (not cheap weed barrier) on the graded soil before the first stone goes down. It stops the sub-base from sinking into soft ground and mixing with the soil, which can cost you an extra inch of stone you never planned for. On firm, well-drained soil you can skip it.

References

  • Site's published density variants (lib/calc.js)
  • ASTM C33 aggregate density ranges
  • UK sub-base terminology (hardcore / MOT Type 1) noted for naming equivalence; quantities use US crusher-run / road-base classes.

Run your own numbers

Reading is good. Math is better. Punch your project into the free calculator and order with confidence.